Weather has been pretty typical for a Washington winter, but for the most part working conditions have been good and Rhine continues to make good progress on prepping the site so that we can start building rather than removing and salvaging.

2/17/12 - Rhine worker cleans up after a productive week.

Early the week of February 20, work continued to mark the existing concrete foundation before cutting and removing parts of it to prepare for installation of new plumbing and footings to support the renovated 2-story Program Center.

2/20/12 - Site Super Stan marks the foundation for saw cutting




We got a break on Wednesday with sunny, though breezy weather.

2/22/12 - Rhine removes sections of concrete foundation to prepare for plumbing and footings