Thursday, February 9, 2012

Building Prep

Clubhouse Interior 2/3/12

Rhine removes debris from Clubhouse 2/3/12
The Tacoma Program Center renovation project is well and truly underway!  The Monday after permits were issued by the City of Tacoma, Merit Construction (the project General Contractor) mobilized it's subcontractor Rhine to commence building prep and abatement work.  That week was blessed with good weather, and Rhine sprung into action, getting a great start on the project.  The good weather continued through the weekend (with sunny, almost springlike weather with high temperatures nearly to 60 deg. F!) into the week of February 6, and Rhine continued to make strong progress.

2/7/12 - Rhine workers strip roofing to prepare for reclamation of decking to be used in new Program Center







1 comment: