Larry has been knocking of the various inspections required to certify completion of the Tacoma Program Center, and Substantial Completion is still anticipated at the end of the week.  The ADA parking spot was cut, formed and curbed last week,
7/20/12 - Pouring the curb, corner of Carr & N. 30th
7/20/12 - Curb poured for ADA parking spot













and Carr Street was paved, the ADA ramp formed and poured this week.

7/23/12 - Finishing up the ADA ramp and sidewalk
7/23/12 - Site Super Larry inspects paved Carr St.

7/24/12 - The gorgeous new Mountaineers ADA parking spot!