![]() |
| 7/20/12 - Pouring the curb, corner of Carr & N. 30th |
![]() |
| 7/20/12 - Curb poured for ADA parking spot |
and Carr Street was paved, the ADA ramp formed and poured this week.
| 7/23/12 - Finishing up the ADA ramp and sidewalk |
| 7/23/12 - Site Super Larry inspects paved Carr St. |
| 7/24/12 - The gorgeous new Mountaineers ADA parking spot! |


No comments:
Post a Comment