Tacoma Water finished their part of the connection of the fire suppression sprinkler system to the City water main running down Carr St. on Thursday,5/24.
 |
5/22/12 - Sprinkler tap to City water main - tap made on live main! |
|
|
 |
5/22/12 - Trench across Carr St. from water main to vault |
On Friday 5/25 the concrete topping slab was poured on the 2nd floor of the Program Center.
 |
5/29/12 - Concrete topping slab looking from 2nd floor classroom through Boardroom to Commencement Bay |
Preparations are complete for an Open House of the Tacoma Program Center on Thursday evening 5/31 from 4 - 8 pm to allow Mountaineers, neighbors and members of the community get a preview of our great facility! Please come - hope to see you there!