By Tuesday of this week the roof decking was completely installed and the roofers were busy completing installation of the roof. After a glorious weekend and Monday, rain returned on Wednesday interrupting the roofers' progress temporarily. With a little luck, the roofing will be complete and the building "dried-in" by the end of the week! Windows are arriving and Merit will start installing them the week of April 30.
 |
4/23/12 - Program Center with nearly-completed roof decking |
 |
4/24/12 - Roof decking complete, roofing in progress |