Tuesday, February 14, 2012

Topless!

Removal of the clubhouse roof beams was completed by early the afternoon of Valentine's day, February 14!  The roof is now completely off of the building and all the beams have been stacked in preparation for salvage and reuse in the new Program Center.

Clubhouse "interior" with only ridge beam remaining

Ridge beam being lowered to the ground

Salvaged rafters stacked for storage and reuse in renovated Program Center

Saturday, February 11, 2012

Roof Decking Salvage

Jess of Rhine Corp. liberates roof decking on 2/10/12
Rhine continued to make good progress the rest of the week, salvaging the fireplace hood, removing the remaining debris from the interior of the Clubhouse and cutting the roof decking for salvage.  On Saturday February 11, a work party of 12 Tacoma Mountaineers met at the Clubhouse to pull nails and staples from the roof decking to prepare it for storage and reuse in the Program Center.  The decking will be used for making doors, wainscoting and other wood panel features on the interior. 
Salvaged decking ready for storage
Marian Shepherd, Tom Bates & Rick Yasger pull nails and staples while Gretchen Roosevelt cleans up

The salvage team congregates for a photo op after a successful day!
Example of stamp on decking
Many of the lengths of roof decking were stamped with the name of St. Paul & Tacoma Lumber Co., which, upon its founding in 1888, set out to build the 'world's largest sawmill' on the Tacoma tideflats!  The decking was installed in 20 ft. lengths and was of such quality that now only exists in memory and salvage.

Thursday, February 9, 2012

"Groundbreaking" Ceremony

On Wednesday, February 8 a "groundbreaking" ceremony was held at the Clubhouse to mark the start of the renovation process (it was discussed that groundbreaking is somewhat of a misnomer as the clubhouse is being rebuilt to a Program Center using many reclaimed elements of the Clubhouse).  Our flirtation with early spring weather abruptly came to an end early the morning of February 8, and we were returned to the typical Tacoma winter conditions of overcast and drizzle.  However the weather did not dampen the spirits of those participating in the event and we had a turnout approaching 50 including local dignitaries, Martinique Grigg and other staff members from Seattle, nearly the entire Tacoma Board, the complete architecture, engineering and construction team, and other interested community members and Mountaineers. 
Local dignitaries, construction team and Tacoma Mountaineers Board at Program Center "groundbreaking"
Geoff Lawrence, Martinique Grigg and Darin Brekke commemorate the start of the Tacoma Program Center project
We're all happy to be underway and once again are thankful for the generous bequest by Brunhilde (Bruni) Wislicenus through The Mountaineers Foundation, which provided the opportunity to realize this renovation.

Building Prep

Clubhouse Interior 2/3/12

Rhine removes debris from Clubhouse 2/3/12
The Tacoma Program Center renovation project is well and truly underway!  The Monday after permits were issued by the City of Tacoma, Merit Construction (the project General Contractor) mobilized it's subcontractor Rhine to commence building prep and abatement work.  That week was blessed with good weather, and Rhine sprung into action, getting a great start on the project.  The good weather continued through the weekend (with sunny, almost springlike weather with high temperatures nearly to 60 deg. F!) into the week of February 6, and Rhine continued to make strong progress.

2/7/12 - Rhine workers strip roofing to prepare for reclamation of decking to be used in new Program Center







Sunday, January 29, 2012

Getting Started!

Finally, after a lengthy permit acquisition process, our full building permits were issued by the City of Tacoma on Friday, January 27, 2012.  Our architect, Amy DeDominicis

Amy DeDominicis, Architect 




and General Contractor, Merit Construction Northwest have been tremendously supportive during this long, often frustrating process.

MCNW Team:  Tom Motland, Scott Seelye, Tammy Birklid,
Kathy Degman, Chris Cody, Neil Shaw, Len Zarelli



and of course Stan Nelson, Project Superintendent!
The week of January 30 will be spent preparing the site for the rehab, and then we are planning to have a formal "groundbreaking" ceremony sometime during the week of February 6.  Keep watching this space for more information!

Wednesday, December 7, 2011

Process Delay

It's early December and we are awaiting issuance of permits from the City of Tacoma to commence work on the Tacoma Program Center renovation.  While we wish that we were two months into the reconstruction process by now, we are not overly surprised that the plan approval and permit process has not proceeded as rapidly as would be ideally desired.  We're still hopeful that we will be able to get started before the end of the year, but are intent to get going whenever the permits are issued.

In the meantime, we have been fine-tuning the Program Center design and have been busy working on various activities to celebrate the centennial celebration of the Tacoma Mountaineers in 2012!  One of the activities that has been undertaken is to publish installments of Tacoma Mountaineers history on a blog.  Be sure to read about the incredibly rich history of the Tacoma Mountaineers in this historical account that will be updated approximately monthly!

Local walk to Dupont - 1916

Sunday, September 11, 2011

Renovation to Commence October 3, 2011!

Merit Construction Northwest (MCNW) has been selected as the renovation project General Contractor from a short-list of three finalists.  Variances were granted by the City of Tacoma for height (small variance) and parking (conditions include addition of ADA parking space and lease for parking spaces on evenings and weekends with a local business), so the major hurdles to realization of the project have been surmounted!  For the rest of September work parties will be cleaning the various material of 55-years worth of occupation from the Clubhouse, and work on the project is scheduled to commence October 3.  Check back frequently for updates.
The Mountaineers - Tacoma Program Center